Trainee facing · Read aloud
Current situation
Campbell Hall work began on 22 March. After four earlier approved progress payments and the later asbestos interruption, Peace Walker Infrastructure Partners, LLC submits Progress Payment Request No. 005 for $4.88 million. Approval would bring cumulative paid progress to $11.23 million.
The on-site COR is incredulous. His signed field memorandum and photographs estimate only 52 percent of the electrical work physically installed, 30 percent of HVAC installed, and no drywall installed, while the contractor claims 65 percent, 60 percent, and 25 percent for those portions. He recommends withholding $2.016 million from the current request. Peace Walker maintains that its percentages follow the accepted progress schedule and schedule of values.
Trainer only · Do not issue
Facilitator context
Release at Increment 17 on 1 September, after [F] and after sufficient asbestos work has allowed interior construction to resume. Give D-01 and D-03 initially. D-03 is a credible installed-work observation, but the COR has not compared his field percentages with the contract's accepted progress schedule, schedule of values, or material-delivery records.
Release D-02 only if trainees ask for the accepted progress schedule or schedule of values, prior-payment history, the basis for Peace Walker's claimed percentages, or records for delivered materials. D-02 shows four earlier approved payments totaling $6.35 million. It also shows explicit August milestones for physical installation and for delivery and protected staging of permanent materials and equipment: 13 percent electrical, 30 percent HVAC, and 25 percent drywall. The contractor achieved and requested exactly those scheduled staging amounts. Joint inventory and receiving records support all $2.016 million questioned by the COR.
FAR 52.232-5(b)(2) permits the Contracting Officer to authorize material delivered on site and preparatory work in the progress estimate. The intended decision is to correct the COR's installed-work-only interpretation and approve the properly substantiated $4.88 million request. Wrongfully withholding the supported $2.016 million creates an avoidable payment dispute. FAR 52.232-27 does not automatically impose Prompt Payment interest while a genuine amount or compliance disagreement exists, but a sustained contractor claim may carry interest under FAR 52.233-1(h). Continue to [K] after either response.
Trainer clue bank
Regulatory signposts
4 sourcesDirect trainees to a citation when they need a narrower clue. Have them apply the contract’s actual clauses, current thresholds, local policy, and the facts before treating any signpost as dispositive.