Increment 1913 Sep 2027Headquarters / Community CenterDecision

Construction wage concerns

Trainees determine whether workers were paid the wage determination's minimum for the classification of work actually performed, not merely the classification written on a certified payroll.

The situation, for each audience

Keep the trainer context out of trainee packets and read-aloud materials.

Trainee facing · Read aloud

Current situation

On 13 September, the Campbell Hall COR sends a factual concern after observing four Volgin Electrical Services, LLC employees installing conduit and raceway, pulling conductors, mounting electrical equipment, and making de-energized terminations. Volgin is Peace Walker Infrastructure Partners, LLC's disclosed electrical subcontractor, but its current certified payroll reports all four as Laborer - Common or General.

Peace Walker transmitted the payroll and says each employee received the reported basic wage and fringe contribution. The incorporated wage determination contains both Electrician and Laborer rates. Payment Request No. 005 was resolved on 1 September, while the task order remains active and its next regular payment cycle follows the 20 September cutoff. Determine what the initial record establishes, what additional compliance checks are warranted, and what amount—if any—must be protected from the next available payment.

Trainer only · Do not issue

Facilitator context

Release K-01 through K-03 at Increment 19 on 13 September, after [D] and regardless of its outcome. Do not reuse D-01 as a pending request: Payment Request No. 005 was resolved on 1 September. This event tests whether a certified payroll is checked against the classification of work actually performed and whether a supported labor withholding is distinguished from the earlier earned-progress decision.

After the initial discussion, use the Trainer Addition. Release K-04 for duration, K-05 for field corroboration, K-06 for worker interviews, K-07 for local area practice, and K-08 for the contractor's explanation. FAR 22.406-6 and FAR 22.406-7 identify payroll examination, onsite inspection, interviews, and comparison with inspector reports or daily logs as normal compliance tools. K-07 keeps the exercise at walk level by resolving the local classification question rather than expecting trainees to know a trade boundary from intuition.

The exercise wage determination sets Laborer at $31.20 basic plus $15.60 fringe and Electrician at $53.40 basic plus $23.10 fringe. The evidence establishes four workers, 120 affected hours each, and a $29.70 hourly difference, producing a $14,256 estimated underpayment. No overtime, split-classification time, conformance, or registered-apprentice issue is included.

Offer only the two listed dispositions. The intended response is to act through Peace Walker as prime, require corrected payrolls and $14,256 restitution, and protect that amount through withholding from the next available payment under FAR 22.406-9 and FAR 52.222-7 while the violation remains unresolved. Adjust or release the withholding after restitution and reconciliation. Preserve evidence and refer suspected knowing falsification through appropriate channels without declaring fraud proven. If trainees suggest stopping every dollar or only correcting future payrolls, say: 'That could fit broader or future noncompliance, but what must happen to these four workers and the supported $14,256 deficiency?'

Trainer clue bank

Regulatory signposts

9 sources

Direct trainees to a citation when they need a narrower clue. Have them apply the contract’s actual clauses, current thresholds, local policy, and the facts before treating any signpost as dispositive.

Give initially

3 records

These establish the decision without answering the factual questions trainees should identify.

K-01

COR wage-classification concern

Reports the work the COR personally observed and the conflicting classification on the current payroll without stating a legal conclusion.

Draft document availablePDF · 1 page · Editable Word copy
K-02

Volgin current certified payroll

Shows four workers reported as Laborer - Common or General for the week ending 10 September, including hours, basic wages, fringe contributions, deductions, and the Statement of Compliance.

Draft document availablePDF · 2 pages · Editable Word copy
K-03

Applicable wage determination extract

Provides only the incorporated Electrician and Laborer rates needed to identify the $29.70 hourly difference.

Draft document availablePDF · 1 page · Editable Word copy

Trainer addition

2 prompts

Give only after trainees have read and discussed the event. Use it to narrow attention without disclosing the answer.

After trainees read and discuss K-01 through K-03, ask: ‘Does a certified payroll establish that the classification is correct, or is it evidence that must be checked against the work actually performed?’

If needed, direct trainees to FAR 22.406-6 and FAR 22.406-7. Those provisions point toward payroll examination, employee interviews, onsite inspection, and comparison with daily reports or logs; they do not make the certification conclusive.

Give only after trainee prompting

5 records

Use the prompt as a release gate; close-enough trainee questions should count when they seek the same underlying fact.

Prompt / triggerHandoutExercise purpose
PromptAsk how long the classification has been used or request earlier payrolls
HandoutK-04
Volgin prior certified payrolls
Draft document availablePDF · 2 pages · Editable Word copy
PurposeAdds Payroll Nos. 025 and 026 to K-02 and establishes three weeks at 40 hours per worker: 480 affected hours in all.
PromptAsk what work the named employees actually performed or request field corroboration
HandoutK-05
Daily inspector reports and site photographs
Draft document availablePDF · 3 pages · Editable Word copy
PurposeConnects the four workers and all three weeks to conduit, conductor, box, panel-equipment, and de-energized termination work through contemporaneous reports and two fictional exercise photographs.
PromptAsk to interview the workers or verify their duties, hours, rates, apprenticeship status, or employer instructions
HandoutK-06
Employee interview records
Draft document availablePDF · 4 pages · Editable Word copy
PurposeFour private interviews confirm the duties and hours, the reported pay, the employer's 'helper/laborer' description, and that none was a registered apprentice.
PromptAsk how local practice classifies the documented work or consult the labor advisor
HandoutK-07
Labor-standards area-practice determination
Draft document availablePDF · 1 page · Editable Word copy
PurposeMakes the walk-level classification issue conclusive: the documented duties are Electrician work in the exercise locality, Electrician is already on the wage determination, and the resulting deficiency is $14,256.
PromptContact the prime or subcontractor for an explanation
HandoutK-08
Contractor response to classification inquiry
Draft document availablePDF · 1 page · Editable Word copy
PurposeGives Volgin's plausible but legally insufficient position that unlicensed helpers supervised by a foreman may be paid as general laborers; it also confirms there are no split-classification time records or registered apprentices.

What a strong analysis should surface

  1. 40 U.S.C. § 3142 and FAR 52.222-6 require at least the wage determination's basic rate and fringe benefits for the classification of work actually performed. Calling electricians general laborers on a certified payroll does not change the work.
  2. The supported restitution is $14,256: four workers × 120 hours × ($76.50 electrician total − $46.80 laborer total).
  3. FAR 22.406-6 and FAR 22.406-7 support the evidence sequence: examine payroll classifications, rates, fringes, hours, and deductions; interview employees; inspect onsite work; and compare payrolls with inspector reports and daily logs.
  4. Administer the issue through Peace Walker as the prime under FAR 52.222-8. Require corrected payrolls, proper classification, and restitution; when the Contracting Officer believes the violation exists, FAR 22.406-9 and FAR 52.222-7 support withholding the $14,256 estimated underpayment from the next available payment due on the active order, then adjusting or releasing the amount after the record is resolved.
  5. Do not reopen [D]. Payment Request No. 005 involved earned progress and was resolved on 1 September. [K] is a later labor-standards issue that affects the next available payment or other accrued amounts due.
  6. Preserve evidence and refer possible knowing falsification through the appropriate labor/fraud channels, but do not state that a criminal violation is proven merely from an inaccurate payroll.

Available response options

2 options

Offer options in plain language and accept equivalent trainee analysis. Do not reveal the assessment labels. Use each availability gate before accepting a contextual response, and use the trainer line to redirect a superfluous answer immediately.

How to run this node: Offer only these two dispositions. K-01 through K-03 are initial. Release K-04 through K-08 only through their investigative gates; K-08 is optional contractor voice, while K-04 through K-07 establish the supported classification and amount. If trainees suggest reopening Payment Request No. 005, stopping every payment, or making only a prospective correction, say: 'That may fit different facts, but [D] is closed. What will you do about these four workers and the supported $14,256 deficiency on the active order?'

K1Weak

Accept the reported Laborer classifications because the payroll is certified and each worker received the wage and fringe amounts shown; release the next payment without a wage withholding.

Available when
Initially available
Trainer line
Certification does not make the classification conclusive. FAR 52.222-6 ties the required rate to the work actually performed, and FAR 22.406-6 and FAR 22.406-7 direct the Government to test payroll data against field evidence and interviews. The later compliance review establishes that all 480 hours were Electrician work and validates a $14,256 deficiency.
Leads next
Peace Walker and Volgin must still correct the payrolls and make restitution, and the Contracting Officer must protect the estimated underpayment from payments due. The unsupported initial disposition produces an avoidable labor-compliance finding and delays correction for the four workers; no separate branch follows.
K2Strong

Complete the payroll, field, interview, and area-practice checks; act through Peace Walker to require corrected Electrician payrolls and $14,256 restitution; and withhold $14,256 from the next available payment while the deficiency remains unresolved.

Available when
Strongest after trainees request and review K-04 through K-07; K-08 may be considered if requested
Trainer line
The response uses the evidence types identified in FAR 22.406-6 and FAR 22.406-7, applies the incorporated Electrician rate to the work actually performed, preserves the prime's payroll responsibility under FAR 52.222-8, and limits withholding to the supported estimate under FAR 22.406-9 and FAR 52.222-7. Volgin's skill-and-supervision argument in K-08 does not displace the actual-work rule.
Leads next
Record the $14,256 withholding against the next payment due, verify corrected payrolls and restitution, reconcile the final amount, and release any excess when permitted. Preserve and refer any evidence suggesting knowing falsification without prejudging it; no separate branch follows.